Drum vs. Batch Plant: Learn the Differences That Will Make Your Asphalt Mix Just Right

2022-10-24 10:54:56

 

 

Often, preparing an asphalt mixture is compared to baking a cake. A contractor needs to make sure he/she has an accurate recipe and proper ingredients and that he/she blends everything at the correct ratios and “bakes” the mixture to produce a beautiful, homogeneous final product that everyone will be happy with – a blend that will perform as anticipated when properly applied on a roadway.

 

There are two basic types of plants that are used in the process of making asphalt mixtures: batch plants and drum plants.




Batch plants make small accurate “batches” of asphalt mixture through a process that is repeated over and over until the total tonnage for a project has been manufactured.

 

 The advantages


  • They offer the highest level of flexibility in production.

  • They manufacture a very high-quality finished product due to the accurate measurement of each batch produced.

  • Batch size and production capacity can vary based on the designs of the plants themselves.

  • Due to the intermittent production process, plant operators can easily switch back and forth between different mix recipes if necessary.






Drum plants, on the other hand, prepare the asphalt mix through a continuous process and require the use of silos for temporary storage prior to the mix being trucked to the paving location.



The advantages


  • There is no interruption in the production process as there is a continuous flow of aggregate and liquid asphalt into the drying/mixing chamber.

  • There are several different configurations of drum plants, all depending on how the aggregate flows in relation to the hot air, which is responsible for heating and drying the materials.

  • In parallel flow, the aggregate and air flow in the same direction through the chamber.

  • In counter-flow plants, the aggregate and air flow in opposite directions through the chamber.

  • In double drum or double barrel plants, there is an outer shell through which the aggregate flows before coming in contact with the hot air inside the chamber.

  • Regardless of the configuration, it is a continuous process that creates a homogeneous mixture that can be manufactured at a high rate (sometimes as high as 600-800 tons per hour).




Main differences:


  • In drum plants, there is no interruption in the production process as there is a continuous flow of aggregate and liquid asphalt into the drying/mixing chamber. There are several different configurations of drum plants, all depending on how the aggregate flows in relation to the hot air, which is responsible for heating and drying the materials. In parallel flow, the aggregate and air flow in the same direction through the chamber. In counter-flow plants, the aggregate and air flow in opposite directions through the chamber. In double drum or Double Barrel plants, there is an outer shell through which the aggregate flows before coming in contact with the hot air inside the chamber. Regardless of the configuration, it is a continuous process which creates a homogeneous mixture that can be manufactured at a high rate (sometimes as high as 600-800 tons per hour). 

  • The ways that aggregate and bitumen (liquid asphalt) are metered into the final mix are different in batch plants and drum plants. In batch plants, the aggregate and asphalt binder are weighted using load cells for accuracy. The aggregate is dried first and then weighted into the pugmill based on the agency-approved Job Mix Formulation (JMF). In drum plants, flow meters and calibrated feed belts are used to measure the liquid and aggregate components into the mixing chamber. Because the drying and mixing are done in conjunction in the drum plant, the need to regularly monitor the moisture content of the aggregate stockpiles is vital to producing a high-quality finished product.







 

Share
Recommended
Why XCMG Backhoe Loaders are Becoming Popular Overseas?
2024-05-08
Why is XCMG Large-tonnage Clamp So popular in Port Construction Site?
2024-04-24
Do you know who is the best partner in mining construction?
2024-04-22
XCMG DTH Drilling Rig Departs South America!
2024-04-17
Three XCMG 20-ton Excavators, which one will you choose?
2024-04-15